Projects · Reservoir & Field Studies

Finding a dozen recompletions in a 30-well East Texas package

A wellbore utility chart showed which zones were spent, which were tested, and which were still worth completing.

Client
East Texas Operator
Location
East Texas
Services
Reservoir & Field Studies
Year
2026

The result

Identified more than a dozen recompletions that added a cumulative 165 BOPD.

The operating question

An East Texas operator wanted to know how much recompletion potential remained across its 30-well package. Over the life of the field, zones had been tested, produced and abandoned in different wells — and no single view showed what was left.

The engineering work

We built a wellbore utility chart for the entire package: a well-by-well, zone-by-zone map showing which intervals had already been tested or produced, and which remained behind pipe.

For the zones that remained, we evaluated whether each was economic to complete.

The action plan

The chart turned a 30-well history into a short list: more than a dozen recompletion candidates in untested or remaining zones that met the economic threshold.

The verified result

  • 12+ recompletions identified across the package
  • 165 BOPD of cumulative added oil production